top of page
F35-A Flying over water

ANTICIPATED PROJECT SCHEDULE

START EIS PROCESS​

Step 1

July 25, 2025

 

Notice of Intent Publication in the Federal Register

Step 2

July 25, 2025 - August 24, 2025

​

Public Scoping Period

​

Step 3

August 28, 2026

​

Draft Environmental Impact Statement (EIS)

Step 4

August 28, 2026 - September 28, 2026

​

Draft EIS Public Comment Period

​

WE ARE HERE - Virtual Public Meeting:
September 15, 2026

Step 5

April 26, 2027

​

Final EIS

Step 6

July 12, 2027

​

Record of Decision

END EIS PROCESS​

bottom of page